Old high court refurbishment

The project involves the removal of loose concrete and  repair of all concrete damage, replacement of all windows for new ones in original form.

Removal of cladding on the rooftop and placement of a new asphalt mineral membranes. Restoning of the entire house.

Main quantities:
Windows 285 units
Roof 1200 sqm
Re-stoning and cladding 2050 sqm

View the building in Google Map.

Customer

The Ministry of Finance

Project start 10. október 2013
Project finish 1. júlí 2014
HVAC design

Efla engineering

Site management Government Construction Contracting Agency
Arcitects Gláma-Kím architects
Structural engineering

Efla engineering

Supervision Government Construction Contracting Agency,

Efla engineering

64.147871,-21.931335|/media/113713/Arnarhvoll_2014.png?w=250&h=109&mode=crop|Old high court refurbishment|/dk/konstruktion/igangvaerende-projekter/old-high-court-refurbishment/| The project involves the removal of loose concrete and repair of all concrete damage, replacement of all windows for new ones in original form. |satellite | yellow | Yderligere