Road to Alftanes
IAV won a contract to build a new road at Alftanes near the capitol area.
The road is about 4 km long, with three pedestrian tunnels, crossroad , exits and one roundabout.
Cabling and piping will also be part of this project which includes hot and cold water, power, both high and low voltage as well as fiber optic cables.
The new road line is both thrugh undisturbed rough lava, vegetated terrain and rebuild part of the old road.
Main quantities:
- Blasting 50.000 m³
- Filling 100.000 m³
- Waterpipes 1.000 m
- Elec. cables 10.000 m
- Asfalt 50.000 m²
- Concrete 1.000 m³
- Concrete formwork 3.000 m²
Customer |
State road administration Town of Gardabær |
Project start | October 2013 |
Project finish | September 2015 |
Main design engineering | Mannvit engineering |
Contractor | ÍAV |
Architects | Gláma - Kím |
Project supervision | State road administration |
64.090526,-21.976568|/media/148293/Alftanesvegur_02.JPG?width=250&height=109&mode=crop|Road to Alftanes|/en/constructions/finished-projects/infrastructure/road-to-alftanes/| IAV won a contract to build a new road at Alftanes near the capitol area. The road is about 4 km long, with three pedestrian tunnels, crossroad , exits and one roundabout.|terrain | blue | Info