News

29. October 2007

Basalt in formation

Since the spring of 2007, designers at Henning Larsen and artist Ólafur Elíasson have been working on the final version of the 12,000 m2 glass shell that will encase the new concert hall and conference centre in downtown Reykjavík’s east harbour area. That design work is now nearing completion. The Board of the East Harbour Project has approved the designers’ fundamental ideas but is waiting with final approval until ideas on the colour scheme have been presented.

The designers’ ideas have evolved toward a view of the building as a creation growing out of a mountain of columnar basalt, where the south side is broken from the mountain so that the columns emerge from it. On the north side, the glass will no longer take the form of columnar basalt, as had been planned initially; rather, it creates a form based on ideas of transected basalt. The east and west sides of the building, which have been shown heretofore as conventional glass walls, will take the same shape, for the most part, as the north side, i.e. transected basalt.

A memorandum of understanding concerning the construction of the glass shell has been signed by IPC and a Chinese glass manufacturer, though the contractual agreement has yet to be finalised. Ólafur Elíasson’s proposals for colour scheme and mirrored glass are expected within a few weeks and will then be considered by the appropriate parties. The set-up of the glass shell is scheduled to begin in the spring of 2008. 

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.

Archive