News

11. September 2012

Búdarháls

At this moment hard work is put into positioning two penstocks which will serve Búðarhálsvirkjun.

The project, that IAV is the main contractor of, consists of: designing, construction, sandblasting, painting and installation of the two penstocks for Búðarhálsvirkjun.

The penstock pipes are each 5.8 meters in diameter and 50 meters in length. The wall thickness of the pipes is 20-22 mm and 560 tons of steel will be used. The pipes are produced in 3-meter tubes, which consist of 6 meter units transferred from the work bays to construction site. The tubes will be 48 and each weighing 18-23 tons. The units are lifted down from the intake structure and down to special made trolley that moves them into place. The trolley is also used positioning the tubes before being fastened down on inserted platforms.

Design work on the project began in October 2011 and pipe construction in January 2012. The first pipes were installed on project site in May. This work has largely been carried out by subcontractors. Verkís Consulting Engineers designed the pipes along with Montavars. Teknis ehf are responsible for the construction and installation of pipes, Verkvík / Sandtak ehf. the sandblasting and painting of the pipe interior after installation. Rittmeyer is responsible for the construction and installation of the flow meters.

Estimated project conclusion is in June 2013, number of employees are 29.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.

Archive