17. March 2010

Construction of Iceland’s highest apartment tower close to completion

The second construction phase in Skuggi will soon come to an end. This phase started late 2006 so it has been worked on for over three years. The original plan included further construction which has now been postponed.

The second phase includes five apartment buildings with 97 flats. The highest tower is 19 stories and rises 68 meters above sea level and is therefore the highest residential building in Iceland.

The outer façade of the buildings is at it’s final stage and most of the buildings are taking on their final shape as seen here below. Only five flats out of 97 have been fitted internally and the rest is unclear.

The main quantities are: 12.500 m3 concrete, 5.100 m2 of windows, 2.800 m2 stone tiles, and 2.600 m2 of other external siding.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.