Good action in the brewery project Olgerdin
At Grjothals 7 – 11 IPC is building a 12.500 m² building for the brewery Olgerdin. The building is on four floors and a basement, standing west of the existing building and accommodates a warehouse and offices.
The building that is more than 12.000 m² is divided into 700 m² basement, approx. 300 m² technicalspaces on the first floor, approx. 8.400 m² warehouse on the first floor of which 1.500 m² are coolers and freezers and approx. 3.200 m² of office space on the second, third and the fourth floor. Also a car park of 3.000 m² on two floors is a part of the project.
Work is being carried out on interior and exterior finishes. The building has been closed and the concrete work of the floors in the warehouse is finished. Erection of the warehouse shelves and platforms has started. The number of workers on the site is now around 120.
The project started in the beginning of 2008 and the warehouse will be delivered ready for use at the end of March 2009, but the office part will be delivered at the end of April 2009.