Good performance in the Sjalandskoli project - elementary school
IPC is now building the second phase of Sjalandskoli in Gardabaer but IPC finished the first phase in 2005.
The second phase consists of a gymnasium, a swimming pool, few different sizes of exercise halls and a multiple use large hall that is used among other things as a canteen and a recreation hall.
These days the building is being closed to make it possible to heat it up, which is important for the next tasks of interior finishes.
The number of workers on the site has been around 30 for the past few months. The project finish is estimated to be in the beginning of July 2009.