Frá vinstri eru Snorri Árnason sölustjóri landvéla hjá Kletti, Einar Már Jóhannesson forstöðumaður tækjareksturs, Bjarni Arnarsson sölustjóri Kletts, Steinþór Páll Garðarsson tækjastjóri, Garðar Óskarsson bílstjóri og Þorsteinn Jónasson bílsstjóri.
From left are Snorri Arnason, Sales Manager of land machines at Klettur dealer, Einar Már Jóhannesson director of heavy machines at IAV, Bjarni Arnarson sales manager from Klettur, Steinþór Páll Garðarsson machine operator, Gardar Óskarsson machine operator and Thorstein Jonasson machine operator.
These days the dealer Klettur is delivering to IAV, four gravel trucks of the type Scania G410 CB 8X4 MHz with Langendorf platform. Klettur is also delivering to IAV three wheel excavators Caterpillar M313D and M315D models, with "Roto Tilt" and fittings for gravel wagon and four telescopic forklift by Caterpillar TH414C equipped with towing hook and sophisticated equipment for man baskets.
The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks.
ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.
ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf.
Sky Lagoon was open to the public on May 1, 2021.
Sky Lagoon website is www.skylagoon.com
Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.
Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.