News

24. June 2008

New N1 filling station at Bíldshöfdi Cape

Iceland Prime Contractor is currently engaged in the construction of a new filling station for N1.

The project involves a substantial enlargement of the lot and the construction of two buildings on the site where N1 has operated a filling station. One of the buildings will be a 515-m2 service centre comparable to those the Company has built for N1 in Fossvogur, on Hringbraut Boulevard, on Borgartún Street, and in the Reykjavík suburb of Mosfellsbaer. The second building will be a 500-m2 tyre and lubrication workshop with a tyre storage warehouse in the basement.

Methane fuel service areas will be improved and an increased number of methane pumps installed on the pumping islands. A methane pipe from the Álfsnes peninsula area will be connected to the station, which will serve as a supply station. The station will also be used as a filling station for methane shipping containers.  The new filling station will be brought into use in early July 2008.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.