24. August 2009

Opening of Sjálandsskóli

In June 2008 IAV started the second phase of the project in Sjálandsskóli elementary school. Included in the project was to build a 3000 square meter building which consist of a gymnasium, a swimming pool, few different sizes of exercise halls and a multiple use large hall that is used among other things as a canteen and a recreation hall. IAV was also the contractor for the first phase of the project which finished in 2005 which was to build 4000 square meter building.

At the project end, an opening ceremony tooke place in Sjálandsskóli today. Students attending the school along with their parents came to the event. Next year, 236 students will be attending the school which is an increase of 55 students from last year. Along with them 50 students are attending the International school which is operating in the same building.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.