14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.

All concrete work will largely be completed by the end of May, followed by support walls and floors. Last winter a lot of working power has been put in to the power system and is that work well on its way as well as finishing work inside. Most of the work is done in the power station these days as well as finishing earthworks.

On Monday May 28th. testing of the power plant's machinery began. Work on the load-bearing on roads is about to begin. Material production of load-bearing materials began in May. Work is being done on project site. When most people worked on the project around 130-140 people were from us.

Today about 80 employees work on the project regularly but are decreasing fast, returning equipment from project site has started.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.