News

11. February 2010

The underground car park at Harpa

An underground car park is being constructed at the Concert and Conference Centre Harpa. This is a fairly large construction on two levels and will be able to house 545 cars.

The main construction quantities are: 23.000 m3 of concrete, 2.350 tons of construction steel and 18.600 m2 of bubble deck plates.

The car park is on the south side of Harpa, by the sea. Seawater will penetrate underneath and around the construction and push the structure upwards. To prevent this ground anchors are being used to keep the building from “floating up”. These anchors as well as a sandwich layer of gravel will keep the structure stable. There are around 500 anchors, each between 12 and 17 meters, drilled into the ground below the bottom plate. See the illustration below.

The project status for the car park is that the bottom plate is almost completed and over 3.000 square meters of the second level is finished. The bottom plate is now being filled up with gravel to increase its weight; the gravel filling is about 12.000 m3. Heavy machinery is used in this filling as the picture shows. Atthe same time construction of the access road to the car park is also being carried out, but the car park will be accessed from Kalkofnsvegur.

Approximately half of this project phase has been completed and the car park will be finished early 2011 at the same time as the main building, Harpa.

 

 

 

 

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.

Archive