17. June 2007

University Square cornerstone laid

At a ceremony held on the 96th anniversary of the University of Iceland, 17 June 2007, the cornerstone was laid for the new University Square complex. In her address at the ceremony, University rector Kristín Ingólfsdóttir said that the new buildings will enable the University to improve vastly the service and support rendered to students.

The cylinder embedded in the cornerstone contains the symbol of the University of Iceland; drawings of the buildings, both printed copies and electronic copies on memory key; and the history of University Square, from the first ideas to the laying of the cornerstone.

Construction of the University Square buildings is on schedule; casting is complete, and the construction of the steel frame is in progress. Levelling of the lot is underway, and in early August the groundwork crew will begin their finishing work. A large portion of the building will be inaugurated at the end of 2007, and the 3rd floor of University Square 2 will be brought into use in February 2008.

Twitter Facebook
Go back

Construction in Keflavík is in full swing
24. June 2021

Construction in Keflavík is in full swing

The design phase in Keflavik which began in the middle of September 2020 has now been completed. The permission to commence is expected within the next few weeks. ÍAV received early permission to carry out the earthworks of the apron to ensure that the concrete paving could commence as early in the summer as possible. ÍAV has dug and removed 120.000 cubic metres of soil and rock and imported 100.000 cubic metres of crushed aggregates since March 9th, 2021.

Sky Lagoon handed over
12. May 2021

Sky Lagoon handed over

ÍAV has handed over the Sky Lagoon project to their client Nature Resort ehf. Sky Lagoon was open to the public on May 1, 2021. Sky Lagoon website is www.skylagoon.com

Móavegur 2-12, Progress Report
30. November 2018

Móavegur 2-12, Progress Report

Since contract signing on Feb 16, 2018, a continuous progress is claimed by ÍAV and sub trades on Móavegur 2-12 project site in Reykjavík. The project is to deliver in a turn-key manner a 155-apartment affordable rental-housing complex entailing six 3-4 storey buildings with a shared underground carpark, with anticipated project completion in June of 2020. The Client Bjarg is a non-profit organization formed by two of Iceland’s largest confederations of labour, ASÍ and BSRB.

Project status on Burfell Power Plant expansion.
14. June 2018

Project status on Burfell Power Plant expansion.

Now about 85% of all construction has been completed on the Burfell power plant expansion. All water chanels have been concluded. The entrance chanel was completed late April and the sewerage chanel was completed in beginning of May.